Measure L Projects
San Bernardino County voters passed the $230-million general obligation bond Measure L in 2002, allowing Chaffey College to fund projects in the Chaffey College Facilities Master Plan. A citizen’s oversight committee meets each quarter to review the financial status and the construction progress. The facilities master plan consists of new construction, infrastructure repair, renovation and upgrades to existing facilities, and procurement of educational equipment. The capital improvement program has made significant progress. This is a summary of the completed projects and construction in progress.
COMPLETED PROJECTS
Architect: | DLR Group |
---|---|
Construction Manager: | Bernards |
Contractor: | RC Construction Services |
Contract Start: | October 11, 2017 |
Contract Completion: | April 14, 2019 |
Original Contract: | $718,000 |
Approved Change Orders | $50,819 |
Revised Contract: | $768,819 |
Scope: The facility received upgrades to provide modern instructional space. The project included infrastructure upgrades (e.g. electrical, lighting, & data), accessibility improvements, new finishes (paint/flooring) and a new digital projection and sound system.
Architect: | DLR Group |
---|---|
Construction Manager: | Bernards |
Contractor: | RC Construction Services |
Contract Start: | October 11, 2017 |
Contract Completion: | April 14, 2019 |
Original Contract: | $2,052,000 |
Approved Change Orders: | $142,917 |
Revised Contract: | $2,194,917 |
Scope: The existing Museum / Gallery will be upgraded and renovated to provide modern gallery space and instructional facilities. The planned renovations will include new HVAC and other infrastructure upgrades, new patio sunshade structure, new gallery lighting, moveable gallery walls; the Props sign installation, and accessibility improvements.
Architect: | DLR Group |
---|---|
Construction Manager: | Bernards |
Contractor: | RC Construction Services |
Contract Start: | October 11, 2017 |
Contract Completion: | April 14, 2019 |
Original Contract: | $2,674,000 |
Approved Change Orders: | $392,736 |
Revised Contract: | $3,066,736 |
Scope: The project scope is to upgrade the Theatre Wings to provide modern instructional space. The planned renovations will include infrastructure upgrades (e.g. electrical, plumbing, & HVAC), new finishes (paint/flooring), accessibility improvements, new lighting, and restroom renovations.
Architect: | DLR Group |
---|---|
Construction Manager: | Bernards |
Contractor: | RC Construction Services |
Contract Start: | October 11, 2017 |
Contract Completion: | April 14, 2019 |
Original Contract: | $3,339,000 |
Approved Change Orders: | $31,215 |
Revised Contract: | $3,370,215 |
Scope: The project scope is the installation of a steel frame shade structure located east of the MACC in the center Quad area to provide for additional dining and gathering space for students. The planned improvements will include charging stations, a snack/vending area, and lighting. DLR Group finalized the DSA back check comments and project details.
Architect: | DLR Group |
---|---|
Construction Manager: | Bernards |
Contractor: | RC Construction Services |
Contract Start: | October 11, 2017 |
Contract Completion: | April 14, 2019 |
Original Contract: | $1,026,000 |
Approved Change Orders: | $71,618 |
Revised Contract: | $1,097,618 |
Scope: The project scope is to provide an exterior gathering location for students and staff. The project will include a new plaza area, landscape & irrigation, modification of traffic routes for service vehicles to the Bookstore, MACC & the costume shop, and relocation of parking and Access Bus drop offs to the adjacent Omnitrans parking lot.
Engineer: | P2S Engineering |
---|---|
Construction Manager: | Bernards |
Contractor: | Southland Industries |
Contract Start: | April 6, 2015 |
Contract Completion: | July 1, 2016 |
Contract Amount: | $3,648,281 |
Approved Change Orders: | $58,486 |
Revised Contract Amount: | $3,706,767 |
Scope:; Installation of a 700,000-gallon thermal energy storage tank (TES) to increase Central Plants cooling capability throughout the Campus infrastructure system. Addition of six new boilers to increase the capacity of the existing heating systems to meet future demands on Campus.
Engineer: | Rodriguez Engineering |
---|---|
Construction Manager: | Chaffey College |
Contractor: | Laird Construction Company, Inc. |
Contract Start: | October 5, 2012 |
Contract Completion: | January 15, 2013 |
Original Contract: | $697,000 |
Approved Change Orders: | $26,966 |
Revised Contract: | $723,966 |
Scope: The project scope is for the Division of State Architect (DSA) close out of the original College Drive (Amber Lane) project, which was completed back in 2005. The new scope of work is for installation of access improvements in the general area of Automotive Technology building (ATL).
Engineer: | Associated Engineers |
---|---|
Construction Manager: | Bernards |
Contractor: | RC Construction Services, Inc. |
Contract Start: | June 21, 2016 |
Contract Completion: | August 12, 2016 |
Original Contract: | $292,800 |
Approved Change Orders: | $14,516 |
Revised Contract: | $307,316 |
Scope: The project includes the construction of a new 116,000 square foot, 260-space decomposed granite parking lot to serve the needs of adjacent athletic fields.
Engineer: | National Roofing Corporation |
---|---|
Construction Manager: | Chaffey College |
Contractor: | Best Contracting Services, Inc. |
Contract Start: | May 22, 2015 |
Contract Completion: | July 5, 2015 |
Contract Amount: | $301,200 |
Approved Change Orders: | ($ 4,000) |
Revised Contract Amount: | $ 297,200 |
Scope: The project is the complete removal and replacement of the roof system at the Business Education building with a single ply PVC roof system.
Engineer: | Chaffey College ITS Staff |
---|---|
Construction Manager: | Chaffey ITS Staff |
Contractor: | CHEC Construction |
Contract Start: | March 9, 2015 |
Contract Completion: | April 9, 2015 |
Original Contract: | $ 19,746 |
Approved Change Orders: | $ 0 |
Revised Contract Amount: | $ 19,746 |
Scope: The project is the installation of a video surveillance system with both interior and exterior cameras locations for full coverage of the Library area.
Engineer: | Fuscoe Engineering, Inc. |
---|---|
Construction Manager: | Bernards |
Contractor: | Excel Paving Company |
Contract Start: | July 2, 2012 |
Contract Completion: | August 3, 2012 |
Original Contract: | $127,965 |
Approved Change Orders: | $0 |
Revised Contract: | $127,965 |
Scope: The project includes the addition of drainage systems at Parking Lot 4 to address storm drain overflow.
Engineer: | Fuscoe Engineering, Inc. |
---|---|
Construction Manager: | Bernards |
Contractor: | Laird Construction/KAR Construction Ryko Construction/Raffi's Metal Design |
Contract Start: | March 19, 2012 |
Contract Completion: | May 31, 2012 |
Original Contract: | $121,832 |
Approved Change Orders: | $6,123 |
Revised Contract: | $127,955 |
Scope: Addition of a concrete pathway from Health Sciences to the Michael Alexander Campus Center.
Engineer: | P2S Engineering, Inc. |
---|---|
Construction Manager: | Chaffey College |
Contractor: | Cavalier Construction/VO Builders |
Contract Start: | September 14, 2011 |
Contract Completion: | April 30, 2012 |
Original Contract: | $105,092 |
Approved Change Orders: | $0 |
Revised Contract: | $105,092 |
Scope: Installation of a prefabricated greenhouse structure at the Science Complex.
Construction Manager: | Bernards |
---|---|
Contractor: | Daniel's Electric Construction, Inc. Black Box Network Services/Siemens |
Contract Start: | November 1, 2011 |
Contract Completion: | January 31, 2012 |
Original Contract: | $71,354 |
Approved Change Orders: | $543 |
Revised Contract: | $71,897 |
Scope: Addition of security cameras and electrical upgrades in the Omnitrans parking lot.
Architect: | MDA Johnson Favaro |
---|---|
Construction Manager: | Bernards |
Contractor: | See Multi-Prime Contracts |
Contract Start: | June 21, 2010 |
Contract Completion: | August 11, 2011 |
Original Contract: | $6,686,215 |
Approved Change Orders: | $216,270 |
Revised Contract: | $6,902,485 |
Multi-Prime Contracts (19): | See Below |
BP 01 - General Construction: USS Cal Builders, Inc. | $643,536 |
BP 02 - Earthwork, Grading & Paving: Crew, Inc. | 774,048 |
BP 03 - Concrete: ASR Constructors, Inc. | 567,496 |
BP 04 - Masonry: ASR Constructors, Inc. | 178,000 |
BP 05 - Structural Steel: KCB Towers, Inc. | 574,290 |
BP 06 - Casework: K & Z Cabinet Co., Inc. | 134,531 |
BP 07 - Roofing & Sheet Metal: Chapman Coast Roof Co., Inc. | 220,449 |
BP 08 - Aluminum Storefront & Glazing: E & R Glass Contractors, Inc. | 167,868 |
BP 09 - Framing, Drywall, Fireproofing, Lath & Plaster: Caston Plastering & Drywall, Inc. | 698,372 |
BP 10 - Ceramic Tile: Continental Marble and Tile Company | 74,104 |
BP 11 - Acoustical Ceilings: Commercial Interiors Acoustics, Inc. | 47,315 |
BP 12 - Flooring: Donald M. Hoover Company | 95,998 |
BP 13 - Painting: Triumph Painting | 65,626 |
BP 14 - Plumbing: Nile ASR/Duke Constructors | 467,902 |
BP 15 - HVAC: West-Tech Mechanical, Inc. | 674,289 |
BP 16 - Electrical: Daniel's Electric Construction Co., Inc. | 927,339 |
BP 17 - Landscape & Irrigation: Martinez Landscaping Co., Inc. | 147,939 |
BP 18 - Fire Protection: JPI Development, Inc. | 92,695 |
BP 19 - Kitchen Equipment: R.W. Smith & Co., Inc. | 350,688 |
Scope: Demolition of the existing Campus Center West Building and the construction of a new 16,400 sq. ft. two story Campus Center Building, including a student cafeteria, faculty dining room, health services, career services resource center, extended opportunity programs and services, and student government offices. Renovation of approximately 1,700 sq. ft. of the existing Campus Center East Building.
Construction Manager: | Bernards |
---|---|
Contractor: | Mission Paving and Sealing, Inc. |
Contract Start: | December 19, 2011 |
Contract Completion: | January 16, 2012 |
Original Contract: | $89,985 |
Approved Change Orders: | $0 |
Revised Contract: | $89,985 |
Scope: Additional road and parking lot work at College Drive.
Architect: | DLR Group WWCOT |
---|---|
Construction Manager: | Bernards |
Contractor: | Southland Industries, Inc. |
Contract Start: | May 31, 2011 |
Contract Completion: | August 7, 2011 |
Original Contract: | $3,155,168 |
Approved Change Orders: | $212,371 |
Revised Contract: | $3,367,539 |
Scope: Energy upgrades, along with interior and exterior renovations, of the Business Education building.
Architect: | HMC Architects |
---|---|
Construction Manager: | Bernards |
Contractor: | See Multi-Prime Contracts |
Contract Start: | March 16, 2010 |
Contract Completion: | June 24, 2011 |
Original Contract: | $ 7,305,036 |
Approved Change Orders: | $ 533,970 |
Revised Contract: | $ 7,839,006 |
Multi-Prime Contracts (17): | See Below |
FABP 01 - General Construction: ISEC, Inc. | $ 621,073 |
FABP 02 - Earthwork, Grading & Paving: Crew, Inc. | 200,216 |
FABP 03 - Concrete: Rossi Concrete, Inc. | 561,334 |
FABP 04 - Fire Protection: Kincaid Industries, Inc. | 167,131 |
FABP 05 - Structural, Misc. Steel & Metal Decking: Columbia Steel, Inc. | 665,962 |
FABP 06 - Casework & Millwork: ISEC, Inc. | 257,679 |
FABP 07 - Roofing & Sheet Metal: Waterproofing Experts, Inc. | 523,021 |
FABP 08 - Aluminum Storefront & Glazing: Best Contracting Services, Inc. | 567,739 |
FABP 09 - Framing, Drywall, Fireproofing, Lath & Plaster: Caston Plastering & Drywall, Inc. | 980,072 |
FABP 10 - Ceramic Tile: J. Colavin & Son, Inc. | 55,184 |
FABP 11 - Acoustical Ceilings: KHS&S Contractors, Inc. | 100,764 |
FABP 12 - Flooring: Donald M. Hoover Company | 167,415 |
FABP 13 - Painting: AJ Fistes Corporation | 92,507 |
FABP 14 - Plumbing: Nile Advanced Construction, Inc. | 398,600 |
FABP 15 - HVAC: West-Tech Mechanical, Inc. | 940,651 |
FABP 16 - Electrical: R.I.S. Electrical Contractors, Inc. | 1,389,997 |
FABP 17 - Landscape & Irrigation: ASR Constructors, Inc. | 149,660 |
Scope: Comprised of 30,400 sq ft., this will be a new academic building. Inside the building, there will be four classrooms, two labs with prep rooms, a library, a bookstore, student lounge, dance studio, and administration offices.
Architect: | P2S Engineering, Inc. |
---|---|
Construction Manager: | Chaffey College |
Contractor: | Siemens Industry, Inc. |
Contract Start: | April 18, 2011 |
Contract Completion: | November 3, 2011 |
Original Contract: | $193,141 |
Approved Change Orders: | $6,238 |
Revised Contract: | $199,379 |
Scope: Upgrade and redesign of existing fire alarm systems at the Campus Center East, Information Services, and Planetarium buildings.
Architect: | HMC Architects |
---|---|
Construction Manager: | Chaffey College |
Contractor: | Daniel's Electric/E & R Glass |
Contract Start: | September 8, 2011 |
Contract Completion: | October 31, 2011 |
Original Contract: | $50,547 |
Approved Change Orders: | $1,805 |
Revised Contract: | $52,352 |
Scope: Installation of an automatic sliding door and upgrades to existing doors at the Student Services/Administration building.
Architect: | NTD Architecture |
---|---|
Construction Manager: | Bernards |
Contractor: | USS Cal Builders, Inc. |
Contract Start: | February 1, 2010 |
Contract Completion: | February 4, 2011 |
Original Contract: | $ 4,694,000 |
Approved Change Orders: | $ 465,508 |
Revised Contract: | $ 5,159,508 |
Scope: Renovation of the 30,843 sq. ft. existing athletics building.
Architect: | P2S Engineering, Inc. |
---|---|
Construction Manager: | Bernards |
Contractor: | Hickman Mechanical, Inc. |
Contract Start: | October 27, 2010 |
Contract Completion: | February 11, 2011 |
Contract Amount: | $ 148,800 |
Approved Change Orders: | $ 12,234 |
Revised Contract Amount: | $ 161,034 |
Scope: The project consists of upgrades to the existing boiler system and expansion tanks at the Central Plant-Phase One
Architect: | Soltis Landscape Services, Inc. |
---|---|
Construction Manager: | Chaffey College |
Contractor: | Nature Tech Landscape |
Contract Start: | September 15, 2010 |
Contract Completion: | February 22, 2011 |
Contract Amount: | $ 105,000 |
Approved Change Orders: | $ 10,210 |
Revised Contract Amount: | $ 115,210 |
Scope: The installation of landscape within the Aviary structure.
Architect: | HMC Architects |
---|---|
Construction Manager: | Bernards |
Contractor: | Young Contractors, Inc. |
Contract Start: | June 4, 2010 |
Contract Completion: | November 24, 2010 |
Original Contract: | $1,681,000 |
Approved Change Orders: | $84,738 |
Revised Contract: | $1,765,738 |
Scope: Design and construction of a new transit bus center for the loading and unloading of the Omnitrans buses on the Rancho Cucamonga campus.
Architect: | Soltis Landscape Services |
---|---|
Construction Manager: | Bernards |
Contractor: | Elite Landscaping, Inc. |
Contract Start: | April 19, 2010 |
Contract Completion: | December 12, 2010 |
Contract Amount: | $ 247,770 |
Approved Change Orders: | $ 10,337 |
Revised Contract Amount: | $ 258,107 |
Scope: The project includes the landscaping and irrigation of the areas adjacent to the Visual and Performing Arts Complex.
Architect: | DLR Group WWCOT |
---|---|
Construction Manager: | Bernards |
Contractor: | Southland Industries |
Contract Start: | June 1, 2010 |
Contract Completion: | July 31, 2010 |
Original Contract: | $ 2,094,591 |
Approved Change Orders: | $ 160,201 |
Revised Contract: | $ 2,254,792 |
Scope: This is an energy project services contract, which includes energy efficient lighting amd HVAC systems and controls, along with interior renovations.
Architect: | DLR Group WWCOT |
---|---|
Construction Manager: | Bernards |
Contractor: | Southland Industries |
Contract Start: | June 1, 2010 |
Contract Completion: | July 31, 2010 |
Original Contract: | $ 893,698 |
Approved Change Orders: | $ 14,908 |
Revised Contract: | $ 908,606 |
Scope: This is an energy project services contract, which includes energy efficient lighting amd HVAC systems and controls, along with interior renovations.
Architect: | HMC Architects |
---|---|
Construction Manager: | Bernards |
Contractor: | KAR Construction/Mobile Modular |
Contract Start: | July 26, 2010 |
Contract Completion: | October 31, 2010 |
Contract Amount: | $275,000 |
Approved Change Orders: | $ 10,419 |
Revised Contract Amount: | $285,419 |
Scope: The installation of a new modular unit for a convenience store for Auxiliary Services located in parking lot no. 12, near the Health Science Building.
Architect: | DLR Group WWCOT |
---|---|
Construction Manager: | Chaffey College |
Contractor: | Peterson Dean Roofing |
Contract Start: | May 21, 2010 |
Contract Completion: | July 31, 2010 |
Original Contract: | $148,700 |
Approved Change Orders: | $0 |
Revised Contract: | $148,700 |
Scope: Replacement of the existing roof on the two wings of the theater complex, to a new standing seam metal roof.
Architect: | Associated Engineers |
---|---|
Construction Manager: | Bernards |
Contractor: | ASR Constructors, Inc. |
Contract Start: | March 15, 2010 |
Contract Completion: | April 28, 2010 |
Contract Amount: | $ 135,000 |
Approved Change Orders: | ($22,828) |
Revised Contract Amount: | $ 112,172 |
Scope: The project includes the renovation of the existing fire lane northeast of the Berz Excellence Building and south of the Language Arts Building. The project will rework existing contours of the fire lane, while connecting it to the new Visual and Performing Arts Complex fire lane in compliance with the Americans with Disabilities Act requirements.
Architect: | NTD Architecture |
---|---|
Construction Manager: | Bernards |
Contractor: | Edge Development, Inc. |
Contract Start: | September 29, 2008 |
Contract Completion: | December 23, 2009 |
Original Contract: | $ 8,560,543 |
Approved Change Orders: | $508,104 |
Revised Contract: | $ 9,068,647 |
Scope: This project consists of a new 22,000 sq. ft. gymnasium. It will include locker rooms and a snack bar.
Architect: | Hammel, Green & Abrahamson, Inc. |
---|---|
Construction Manager: | Bernards |
Contractor: | ProWest Constructors |
Contract Start: | February 2008 |
Contract Completion: | |
- Bldg. B & C- Ceramic Lab/Art Studio | Summer 2009 |
- Bldg. F -Art Complex | Fall 2009 |
- Bldg. E- Music Building | Summer 2009 |
Original Contract: | $ 22,145,000 |
Approved Change Orders: | $ 2,211,142 |
Revised Contract: | $ 24,356,142 |
Scope: This project is comprised of four buildings—two new buildings and two buildings that will be renovated. The 46,000 sq. ft. Performing Arts Building, is a three-story structure, including an art complex, digital media labs, photo studio, dance studio, and post-production lab, art studio, audio lab, interior design lab, lecture rooms, and faculty offices. Additionally, there is a 5,500 sq. ft. one-story Music Rehearsal Building, and includes instrumental and choral rooms. The two existing buildings were renovated and modernized into a Ceramics Lab and Fashion Art Studio.
Architect: | P2S Engineering |
---|---|
Construction Manager: | Bernards |
Contractor: | T & D Communications, Inc. |
Contract Start: | May 14, 2009 |
Contract Completion: | November 6, 2009 |
Original Contract: | $ 154,882 |
Approved Change Orders: | $ ($5,127) |
Revised Contract: | $ 149,755 |
Scope: The Data and Telecom Cabling project involves the installation of new data and fiber cabling for the Visual and Performing Arts Complex, New Gymnasium, and the Physical Science Building. The work was separated into three (3) phases: Phase I-New cabling to the Fashion, Ceramics, and Music buildings in the Performing Arts Complex and the Physical Science Building; Phase II-New cabling to the Stadium Press Box and New Gymnasium; and Phase III-New cabling to the Performing Arts Building in the Performing Arts Complex.
Architect: | HMC Architects |
---|---|
Construction Manager: | Bernards |
Contractor: | Bogh Engineering, Inc. |
Contract Start: | May 11, 2009 |
Contract Completion: | October 5, 2009 |
Original Contract: | $ 1,089,000 |
Approved Change Orders: | $ 42,618 |
Revised Contract: | $ 1,131,618 |
Scope: The Fontana Phase III Parking Lot project consists of the construction of a new parking lot, landscaping, driveway/fire lanes, walkways, utilities, lighting, and signage at the Fontana Campus.
Architect: | MDA Johnson Favaro |
---|---|
Construction Manager: | Chaffey College |
Contractor: | Laird Construction Co., Inc. |
Contract Start: | June 15, 2009 |
Contract Completion: | August 15, 2009 |
Original Contract: | $ 414,550 |
Approved Change Orders: | $ 35,437 |
Revised Contract: | $ 449,987 |
Scope: The construction of a 100,000 sq. ft. parking lot with 194 parking stalls south and west of the existing parking lots.The parking lot is adjacent to the existing Main Instructional Building located on the Chino Campus.
Architect: | P2S Engineering |
---|---|
Construction Manager: | Bernards |
Contractor: | Siemens |
Contract Start: | May 15, 2009 |
Contract Completion: | August 14, 2009 |
Original Contract: | $ 2,700,000 |
Approved Change Orders: | $ 103,828 |
Revised Contract: | $ 2,803,828 |
Scope: Energy project upgrade to the Language Arts and Social Science buildings, which includes installation of new air handling equipment and new lighting systems.
Architect: | WWCOT Architect |
---|---|
Construction Manager: | Chaffey College |
Contractor: | Cabral Roofing and Waterproofing Corp. |
Contract Start: | May 21, 2009 |
Contract Completion: | July 17, 2009 |
Original Contract: | $ 623,636 |
Approved Change Orders: | $ 0 |
Revised Contract: | $ 623,636 |
Scope: Replacement of the existing roof at the Physical Science building with a standing seam metal roof.
Architect: | Steve Frenken Landscape Architecture |
---|---|
Construction Manager: | Bernards |
Contractor: | Land Forms Landscape Construction |
Contract Start: | August 20, 2008 |
Contract Completion: | November 25, 2008 |
Original Contract: | $385,000 |
Approved Change Orders: | ($450) |
Revised Contract: | $384,550 |
Scope: This project consists of landscaping and creating the irrigation system for the Fontana Campus Phase II project and the library lawn area at the Rancho Cucamonga campus.
Architect: | WWCOT Architects |
---|---|
Construction Manager: | Bernards |
Contractor: | Best Contracting Services, Inc. |
Contract Start: | January 1, 2008 |
Contract Completion: | June 13, 2008 |
Original Contract: | $456,169 |
Approved Change Orders: | $16, 383 |
Revised Contract: | $472,552 |
Scope:;Comprised of the Health Science Building and the two Life Science buildings, the Health and Life Science Re-Roofing Project, consists of the removal of an existing built up roof on all three locations, and the construction of a new standing seam metal roof.
Architect: | WWCOT Architects |
---|---|
Construction Manager: | Bernards |
Contractor: | PW Construction, Inc. |
Contract Start: | June 16, 2007 |
Contract Completion: | Phase 1: June 18, 2008 Phase 2: August 15, 2008 |
Original Contract: | $8,196,500 |
Approved Change Orders: | $871,357 |
Revised Contract: | $9,067,857 |
Scope: Comprised of 22,997 sq. ft., the Physical, Health, and Life Science Project consists of the renovation of five existing buildings.
Architect: | Hammel, Green & Abrahamson, Inc. |
---|---|
Construction Manager: | Bernards |
Contractor: | Quiel Bros. Electric Sign |
Contract Start: | December 27, 2007 |
Contract Completion: | June 2008 |
Original Contract: | $180,000 |
Approved Change Orders: | $1,500 |
Revised Contract: | $181,500 |
Scope: Removal and replacement of the existing marquee sign located at the Haven Avenue entrance. The new marquee sign is a double-sided display board constructed of brushed aluminum and baked enamel surfaces.
Architect: | GKK Works |
---|---|
Construction Manager: | Bernards |
Contractor: | Edge Development, Inc. |
Contract Start: | May 16, 2007 |
Contract Completion: | November 11, 2007 |
Original Contract: | 1,897,007 |
Approved Change Orders: | $68,534 |
Revised Contract: | $1,965,541 |
Scope: This project completely re-constructs Parking Lot 12 (Phase 1) including two accessible parking areas, sidewalks, lights and landscaping. An elevator (Phase 2) was also constructed connecting the VSS facility to Parking Lot 12.
Program Budget
Program Fund Sources
(Includes Rancho Cucamonga, Fontana and Chino Campuses)
Fund Source | Amount | Percentage of Total |
---|---|---|
Original Measure L Bond | $229,830,000 | 69.61% |
Bond Refinance Proceeds | $2,300,000 | 0.70% |
Accrued Bond Interest | $18,940,312 | 5.74% |
Other Funds | $79,084,780 | 23.95% |
Total Program Funds | $330,155,092 | 100.00% |
Fund Source | Amount | Percentage of Total |
---|---|---|
Original Measure L Bond | $229,830,000 | 91.54% |
Bond Refinance Proceeds | $2,300,000 | 0.92% |
Accrued Bond Interest | $18,940,312 | 7.54% |
Total Measure L Bond Funds | $251,070,312 | 100.00% |
Program Committed Costs
(Includes Rancho Cucamonga, Fontana and Chino Campuses)
Total Program Funds | $330,155,092 | 100.00% |
---|---|---|
Committed (Expensed or Encumbered) |
$319,658,889 | 96.82% |
Allocated to Projects | $6,113,695 | 1.85% |
Remaining Balance | $4,382,507 | 1.33% |
Total Measure L Bond Funds | $251,070,312 | 100.00% |
---|---|---|
Committed (Expensed or Encumbered) |
$240,773,380 | 95.90% |
Allocated to Projects | $5,914,425 | 2.36% |
Remaining Balance | $4,382,507 | 1.75% |